[Tp.backoffice] PM Achievement WK18

Moustafa Fouad moustafa.fouad at talkpool.com
Tue May 4 20:26:55 MDT 2021


Dear Bernst

Double check attach data after amendment , major two issues


  1.  Same site can not be repeated as a done
  2.  Site where appear in WFM at 3rd , 4th may , planed in 1st may ,  it shall be consider as done in 1st May


Kindly confirm attach data correct



Thanks
Moustafa Fouad

From: bernst.nestor at tpmanagementsa.com <bernst.nestor at tpmanagementsa.com>
Sent: Tuesday, May 4, 2021 12:51 PM
To: Moustafa Fouad <moustafa.fouad at talkpool.com>
Cc: Gerry Bolante <gerry.bolante at talkpool.com>; Bernard Yacoub <bernard.yacoub at talkpool.com>; tp.backoffice at tpmanagementsa.com; jean.jacques at tpmanagementsa.com; eliphene.peterson at tpmanagementsa.com
Subject: RE: PM Achievement WK18

Hello Moustafa,

Please received the weekly report of PM Achievement for the week18 as represented in table below.

Row Labels
Count of Sites ID
Count of Done Date

26-Apr
110
63
Row Labels
Done on WFM
Not On WFM
Not Done
Grand Total
27-Apr
69
45
26-Apr
61
2
47
110
28-Apr
50
41
27-Apr
45
24
69
29-Apr
89
52
28-Apr
41
9
50
30-Apr
41
30
29-Apr
51
1
37
89
1-May
94
64
30-Apr
30
11
41
Grand Total
453
295
1-May
63
2
29
94
Grand Total
291
5
157
453

Regards
Bernst



From: bernst.nestor at tpmanagementsa.com<mailto:bernst.nestor at tpmanagementsa.com> <bernst.nestor at tpmanagementsa.com<mailto:bernst.nestor at tpmanagementsa.com>>
Sent: Wednesday, April 28, 2021 1:05 AM
To: 'moustafa.fouad at talkpool.com' <moustafa.fouad at talkpool.com<mailto:moustafa.fouad at talkpool.com>>
Cc: 'gerry.bolante at talkpool.com' <gerry.bolante at talkpool.com<mailto:gerry.bolante at talkpool.com>>; 'bernard.yacoub at talkpool.com' <bernard.yacoub at talkpool.com<mailto:bernard.yacoub at talkpool.com>>; 'tp.backoffice at tpmanagementsa.com' <tp.backoffice at tpmanagementsa.com<mailto:tp.backoffice at tpmanagementsa.com>>; 'jean.jacques at tpmanagementsa.com' <jean.jacques at tpmanagementsa.com<mailto:jean.jacques at tpmanagementsa.com>>; 'eliphene.peterson at tpmanagementsa.com' <eliphene.peterson at tpmanagementsa.com<mailto:eliphene.peterson at tpmanagementsa.com>>
Subject: PM Achievement WK17

Hello Moustafa,

Please received the weekly report of PM Achievement for the week17 as represented in table below.

Plan Date
Count of Sites ID
Count of Done
%Tage Done
19-Apr
93
84
90%
20-Apr
104
100
96%
21-Apr
78
66
85%
22-Apr
106
89
84%

Count of Sites ID
Column Labels



23-Apr
71
48
68%

Plan Date
Done on WFM
not on WFM
Not Done
Grand Total
24-Apr
52
35
67%

19-Apr
83
1
9
93
Grand Total
504
422
84%
20-Apr
98
2
4
104
21-Apr
65
1
12
78
22-Apr
86
3
17
106
23-Apr
48

23
71
24-Apr
33
2
17
52
Zone
Count of Sites ID
Count of Done WFM
%Tage
Grand Total
413
9
82
504
North
224
189
84%
PAP
148
124
84%
South
132
109
83%
Grand Total
504
422
84%

Regards
Bernst G. NESTOR


-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://tpmanagementsa.com/pipermail/tp.backoffice_tpmanagementsa.com/attachments/20210505/0e922d2f/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: D-PMR Tracker up to 02 May 2021.xlsx
Type: application/vnd.openxmlformats-officedocument.spreadsheetml.sheet
Size: 4431768 bytes